OFFSHORE CONSTRUCTION OVERVIEW
Following the completion of the landfall horizontal directional drill to install ducts in early 2023, offshore construction started in September 2023 with the first phase of the installation of Sofia's two 220 kilometres long export cables. The brand new vessel Leonardo da Vinci has carried out the work, in two phases.
Work on the Dogger Bank site started in 2024 with the installation of the first of the project's 100 extended monopile foundations, delivered by the vessel Aeolus. 2024 was a busy year with the installation of the export cables, foundations, 350 kilometres of array cables and, at the heart of the wind farm, the 13,000 tonne offshore converter platform and its 7000 tonne jacket foundation.
2025 has already seen its first major milestone, with the installation of the first of the 14MW turbines.
Soon we will be fitting turbines with recyclable blades.
Looking across 2025, we expect to complete the foundation and array cable installations, commission and energise our onshore and offshore platforms, and generate first power.
Construction is anticipated be completed by the end of 2026.