OFFSHORE CONSTRUCTION OVERVIEW
RWE’s Sofia Offshore Wind Farm is set to become one of the largest single offshore wind farms in the world, and is the most advanced construction project anywhere in RWE’s global portfolio.
The offshore construction effort began in September 2023 and has been ongoing continuously since then. In less than three years the Sofia team and its contractors, working around the clock, have passed multiple key milestones, and also made huge advances for the industry as a whole.
Following the completion of the landfall horizontal directional drill to install ducts in early 2023, offshore construction started in September 2023 with the first phase of the installation of Sofia's two 220 kilometres long export cables. The brand new vessel Leonardo da Vinci carried out that work in two phases.
Work on the offshore site started in 2024 with the installation of the first of the project's 100 extended monopile foundations, delivered by the vessel Aeolus. Over the rest of 2024 we saw the second phase of the export cable installation, the ongoing installation of the foundation pieces along with 350 kilometres of array cables, and, at the heart of the wind farm, the arrival of the 13,000 tonne offshore converter platform, installed upon its 7000 tonne jacket foundation.
Moving into 2025, the Sofia project welcomed the arrival of the turbine installation vessel, the Wind Peak. As the Van Oord vessels Aeolus and Calypso made steady progress installing foundations and array cables, the Wind Peak began installing the wind turbines themselves. This included all 150 of our recyclable turbine blades. By the end of 2025, we had installed all of the foundations and array cables, and more than half of our turbines.
From there, moving into 2026, our task narrows down to the installation of our remaining wind turbines, commissioning and energisation our onshore and offshore platforms, and then generating first power. We look forward to reporting on these milestones over the rest of 2026.