Onshore Construction

ONSHORE ROUTE MAP

Onshore Map

ONSHORE CONSTRUCTION OVERVIEW

The power produced by Sofia will be transmitted by offshore cables that arrive on land at a site between Redcar and Marske-by-the-Sea. Each offshore cable will connect to an onshore buried cable that will run seven kilometres to a new converter station to be constructed on a site adjacent to the Wilton Complex. Further buried cables will transport the power two kilometres from the converter station to the existing substation at Lackenby, where it will feed into the national grid. Onshore construction works will begin at the site of the onshore converter station in Spring 2021.

Introduction

WHAT'S HAPPENING ON SITE

Work will soon begin to prepare for the start of construction of the onshore electrical infrastructure for Sofia – known as the enabling works - a contractor is due to move into the site in Spring 2021, with pre-preparatory works now underway.

Contractors working for Sembcorp are diverting potable and raw water pipes around the converter station site, at the same time confirming the location of other buried services likely to be affected by the construction. This Sembcorp work will continue into Spring 2021 and will include excavation and pipe laying on the plot of land between the existing mounds near Lazenby and the Wilton South Gate entrance.

Some vegetation clearance has been undertaken as part of the water pipe diversion works. Earlier in the year further vegetation clearance was required to make way for the creation of a temporary access road to the south east of the site, temporary construction compounds and part of the haul road.

ONSHORE CONSTRUCTION TIMETABLE

Early 2021

Start of enabling works to prepare for the construction of the converter station.

Start of formation of the mounds at Lazenby. Reprofiling and increasing the height to screen the converter station site.

Late 2021

Enabling works completed at the converter station site.

Work at the existing National Grid Lackenby Substation begins.

Early 2022

Construction of Sofia’s onshore converter station begins.

Start of works along the cable corridor from landfall to Lackenby Substation. Trenching and duct laying underway.

Mid 2022

Start of two years construction activity at the landfall between Redcar and Marske-by-the-Sea, including horizontal directional drill under the beach to lay ducts for the offshore cable.

Early 2023

Start of installation of the cables from shore to the converter station and from the converter station to the substation.

Mid 2023

Completion of work along the cable corridor from the converter station site to the substation.

Mid 2024

Completion of construction works at the landfall site.

Completion of the installation of cables from shore to the converter station.

Late 2024

Sofia connected to the national grid. All work, including reinstatement, completed along the cable corridor between the converter station and substation, and at the substation itself.

Onshore converter station construction completed.

Completion of the mounds screening the converter stations.

Early 2025

Completion of reinstatement of cable corridor from shore to the converter station site.

SUBMITTED PLANS

All relevant plans relating to the project's onshore construction, including Design, Landscape, Fencing and Drainage, will be submitted to Redcar & Cleveland Borough Council for approval prior to work starting. The button below takes you to a list of all the available documents and their reference numbers so you can find them in the Planning Register of the Council website.

ONSHORE CONTRACTORS

CONTRACTOR LOGO NAME DESCRIPTION WEBSITE

GE's Grid Solutions

Starting onsite in 2022, GE's Grid Solutions will be responsible for the construction of the onshore converter station.

GE's Grid Solutions

Prysmian Group

Prysmian Group will design, supply, install and commission Sofia's HVDC export link including 15km of onshore cables and installation work.

 

Prysmian Group

 

Loading...